Connections terms and conditions
Connections terms and conditions
New distributed generation connections will have additional terms and conditions applied from 1 April 2017. These terms include a number of milestones intended to release capacity from non-moving projects, as part of our commitment to manage capacity fairly for all connecting customers.
- New connection up to 60kVA
- New connection 60kVA - 300kVA (valid from 03/04/2017)
- New connection 60kVA-300kVA (expired 02/04/2017)
- New connection over 300kVA major projects (valid from 01/01/17)
- New connection over 300kVA major projects (expired 29/12/16)
If you are applying for a connection less than 60kVA as a business, then irrespective of the size of your connection, the 60kVA-300kVA terms and conditions will apply. Generally, major projects at extra high voltage scale start at 300kVA but will depend on the local network limitations.