Quotation
The documents shown below are guidance for completing and application form and associated required plans using this information will prevent any delays in providing you with a quotation.
If you are emailing this information to Streetlighting@enwl.co.uk please be aware you will receive an email receipt of confirmation the application has been received.
Please complete our new online application service, if you are a repeat user you can create an account to manage your applications.
If the information is not complete you application will not be processed and we will contact you for the missing information.
Your Quotation will be produced within 25 working days from the receipt of all the correct information.
Following an acceptance of a quotation we will connect your street lights as agreed with the customer. Our service level is 25 working days from acceptance if your site is ready.
Please ensure the site specification is correct installing red ducting as per the quotation pack that will be posted to you.
For any queries at this stage please contact us on 0800 048 1820 option 2.
-
Rent a Jointer
Our rent a jointer scheme allows a customer to use Electricity North West Jointing resource on a pre arranged regular basis.
If you wish to look at this option see the attached documentation for further detail and contact us Streetlighting@enwl.co.uk and we will make contact within 5 days of receiving the query.
-
Tripartite Agreement
Our tripartite agreement is to enable a Local Authority to use a third party Independent Connections Provider to carry out their disconnections and transfers.
For more information please read the attached documentation and to progress your enquiry please contact Malcolm Rogers on 01772 848227
Related items:
Tripartite Agreement for unmetered connections
-
Local Authority
Local Authorities due to the regular volume of work processed do not need to apply for a quotation; there is a call off process in place which can be found below.
There is a guaranteed standard to complete all works within a order of less than 100 cols within 35 days of the full site being ready.
We have regular Steering groups and workshops to improve our processes with the Local Authorities, if you would like more information about this please email christina.Bray@ENWL.co.uk
-
GSoP
The Guaranteed Standards of Performance were implemented in October 2010 by OFGEM for all Electricity Distribution Network Owners.
For a single phase connection the following Standards apply:-
| | Category | Timescale | Late Penalty |
| 1 | ECGS9– Quotation Produced | 25 working days | £10 Daily |
| 2 | ECGS10a – Connection Date (New Site) | As agreed with customer | £10 Daily |
| 3 | ECGS10b – Connection date (Adopted highway) | 35 working days | £10 Daily |
For further information on all Guaranteed Standards of Performance please click here.