If you would like an electricty supply requiring more than 60kVA, you will need to apply for a three phase new connection.

Typically this size of supply is for larger consumers of electricity.

If you require a supply of less than 60 kVA, please see the small business service offering.

Applying for a three phase new connection

When applying for a large industrial or commercial connection, from receipt of the full information required at application stage we will issue a quotation within:

  • 25 working days for a low voltage connection.
  • 35 working days for a high voltage connection.

Once you have received your quotation, it is valid for a 3 month period from the date of issue.

Budget estimate

We will also provide a budget estimate for the work.

  • A request of less than 1 MVA will be estimated at 10 working days.
  • Requests over 1MVA will be esitmated at 20 working days.

The end to end process is covered by the Guaranteed Standards of Performance (GSoP) a summary of which is shown below:

  • Application

    The documents shown below are guidance for completing the application form and any associated required plans. Using this information will prevent any delays in providing you with a quotation.

    If you are emailing this information to connections.enquiries@enwl.co.uk please be aware you will receive an email receipt of confirmation the application has been received and no file over 8MB will be accepted.

    If you are faxing or posting the information you will receive a text within 24 hours of Electricity North West confirming receipt of the information.

    If the information is not complete your application will not be processed and we will contact you for the missing information.

    For any queries at this stage please contact us on 0800 048 1820 option 2.


    Related items:

    Please complete our new online application service, if you are a repeat user you can create an account to manage your applications.

    Application form Electricity Connection (PDF)

    Application form Electricity Connection (online form)

    Guidance for completing over 60 kVA application

     

  • Quote & Acceptance

    Your Quotation will be based on the lowest design cost option from the information provided by yourself. The quote will be accompanied by a quotation guidance pack which will provide you with all the details you require for completing your connection.

    Within your quotation it is important that you read the project specification as this will outline any assumptions made by Electricity North West

    Your acceptance must be accompanied with details of

    • Your electricity provider
    • Zero Vat form if your quotation shows zero vat.
    • Letter of Authority if the Cheque being paid is not the name of original applicant or your are a consultant acting on behalf of the applicant

    An incomplete acceptance will mean that your cheque is not processed and we will contact you regarding the missing information and this will cause a delay to your connection

    For any queries at this stage please contact us on 0800 048 1820 option 3.


    Related items:

    Terms and conditions commercial

    Customer acceptance form guidance

    Legal consents

     

  • Planning & Dates

    Once your acceptance has been processed Electricity North West will contact you about scheduling in your connection. The time scales for us contacting you depends upon the voltage of your connection. The timescale are:

    LV Demand & LV Generation within 7 working days of payment being made

    HV Demand & HV Generation within 10 working days of payment being made

    EHV Demand & EHV Generation within 15 working days of payment being made

    At this point if you are not the person dealing with the site installation it is important, to prevent any delays, that the details of the Site Contact are provided.

    Once it is confirmed that your site is ready your work will be released and a site visit will be arranged to ensure the details are correct.

  • Site Works

    The Delivery team who arrive on site to carry out your connection will carry out all works in accordance with Electricity North West H&S policies, they will have full work instructions and will not carry out the work if on site they find:

    • Black ducting installed
    • Incorrect depth of ducting
    • Substation buildings not completed
    • Scaffolding of other obstructions in the way

    The works to be completed will be as per the quotation this will include all excavation and permanent reinstatement within the public highway.

    For any queries at this stage please contact us on 0800 048 1820 option 3.


    Related items:

    Guidance for temporary supply onsite for over 60 kVA

    Guidance for Outdoor Meter reading Facilities

    Guidance of PME for Electrical Installations

    Guidance for Interference of with Supply

     

  • Metering

    Electricity North West does not supply electricity and therefore we do not install meters, so you will need to arrange for your supplier to install a meter following the installation of the service by Electricity North West.

    Your appointed supplier will require your MPAN number which we will provide following acceptance of your quotation.

    To locate Electricity Supplier please see direct.gov.uk.

    For all other metering enquiries please contact your supplier.

  • GSoP

    The Guaranteed Standards of Performance were implemented in October 2010 by OFGEM for all Electricity Distribution Network Owners.

    For a connection the following Standards apply:-

      Category Timescale Late Penalty
    1. ECGS2A – Provision of Budget estimate <1MVA 10 working days £50 one off payment
    2. ECGS2B – Provision of Budget estimate >1MVA Within 20 working days £50 one off payment
    3. ECGS3A – Provision of any other LV Demand quotation Within 25 Working days £50 Daily payment
    4. ECGS3B – Provision of an HV Demand quotation Within 35 Working days £100 Daily payment
    5. ECGS3C – Provision of an EHV Demand quotation Within 65 Working days £150 Daily payment
    5. ECGS4B Contact customer (post acceptance) about scheduling other LV demand connections Within 7 Working days £50 Daily payment
    6. ECGS4C Contact customer (post acceptance) about scheduling other HV demand connections Within 10 Working days £100 Daily payment
    7. ECGS4D Contact customer (post acceptance) about scheduling other EHV demand connections Within 15 Working days £150 Daily payment
    8. ECGS5 Commence LV, HV and EHV Demand work As Agreed with customer £50 one of payment
    9. ECGS6B – Complete LV Works As Agreed with customer £100 Daily payment
    10. ECGS6C– Complete HV Works As Agreed with customer £150 Daily payment
    11. ECGS6D – Complete EHV Works As Agreed with customer £200 Daily payment
    12. ECGS7B– Complete Energisation As Agreed with customer £100 Daily payment
    13. ECGS7C Complete Energisation HV Works As Agreed with customer £150 Daily payment
    14. ECGS7D– Complete Energisation EHV Works As Agreed with customer £200 Daily payment

    For further information on all Guaranteed Standards of Performance please click here.

Are you a priority customer?

We appreciate that some customers have additional requirements and may have circumstances where a priority service is needed for a variety of reasons.

Learn more

Knowledge centre

Find answers to questions about Electricity North West, including details on electricity connections, power cuts and general enquiries.

Check out frequently asked questions and our user guides.

Read more