Grid code
For connection of large or medium sized embedded generation (normally for capacity of 50MW or more) it will be necessary to satisfy NGET requirements contained within the grid code.
- Connection of large demands and all generation has to comply with the distribution code.
- Large generators (>50MW) also have to comply with the grid code.
Please view the grid code on the NGET website at www.nationalgrid.com/uk.
DG Connection Guide
There is a technical guide on the process of connection aimed specifically at generators. To access the guide please follow the link to the technical guide.